Dept. of Trans. PROGRESS Serial No. Contract No. 04-114-12-40 07-002304 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 29% 35% 07-LA-101-14.9/15.9 Federal Project: ACNH-Q101(41) Progress payment No. 05 Payment period ending: 04-20-04 PKB CONSTRUCTION INC P O BOX 661717 ARCADIA CA 91066 Escrow No. 02153 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,361,626.25 342,659.20 2.a. Extra Work 3,735.32 3,735.32 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 1,365,361.57 346,394.52 5. Mobilization 151,138.35 31,818.60 6. Total Work Completed 1,516,499.92 7. Deductions -10,000.00 0.00 8. a.Contract Retentions -103,455.09 -1,558.38 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 1,403,044.83 376,654.74 10. Reduction Amt to Escrow 11. Payment to Escrow 103,450.00 12. Net Pymt. this Estimate 376,654.74