Dept. of Trans. PROGRESS Serial No. Contract No. 05-171-06-57 07-002304 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 96% 100% 07-LA-101-14.9/15.9 Federal Project: ACNH-Q101(41) Progress payment No. 20 Payment period ending: 06-20-05 PKB CONSTRUCTION INC P O BOX 661717 ARCADIA CA 91066 Escrow No. 02153 Total Estimate This Estimate 1. Contract Itms Without Mobil. 4,824,012.06 127,660.80 2.a. Extra Work 518,069.86 50,942.42 b. Adjustment Comp. 60,415.61 -24,268.46 3. Materials on Hand 0.00 -60,000.00 4. Earned Subject to Retention 5,402,497.53 94,334.76 5. Mobilization 159,093.00 0.00 6. Total Work Completed 5,561,590.53 7. Deductions 8. a.Contract Retentions -270,124.88 -4,716.74 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 5,291,465.65 89,618.02 10. Reduction Amt to Escrow 11. Payment to Escrow 270,120.00 12. Net Pymt. this Estimate 89,618.02