Dept. of Trans. PROGRESS Serial No. Contract No. 11-265-10-30 07-002344 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 19% 35% 07-LA-710-22.5/22.7 Federal Project: NH-7101(801) Progress payment No. 06 Payment period ending: 09-20-11 WESTERN STRUCTURES 6005 TYLER STREET RIVERSIDE CA 92503 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 400,131.17 17,931.34 2.a. Extra Work 14,217.15 14,217.15 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 414,348.32 32,148.49 5. Mobilization 37,500.00 0.00 6. Total Work Completed 451,848.32 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 451,848.32 32,148.49 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 32,148.49