Dept. of Trans. SEMI-FINAL Serial No. Contract No. 05-172-14-31 07-002354 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 07-LA-60-15.1/16.9 Federal Project: ACNH-P060(118) Progress payment No. 25 Payment period ending: 11-30-04 D W POWELL CONSTRUCTION INC P O BOX 1406 FONTANA CA 923341406 Escrow No. 02043 Total Estimate This Estimate 1. Contract Itms Without Mobil. 4,512,194.22 8,705.00 2.a. Extra Work 103,583.13 7,140.76 b. Adjustment Comp. -4,500.00 0.00 3. Materials on Hand 4. Earned Subject to Retention 4,611,277.35 15,845.76 5. Mobilization 450,000.00 0.00 6. Total Work Completed 5,061,277.35 7. Deductions 8. a.Contract Retentions -226,886.17 0.00 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 226,886.17 0.00 9. Total pay to Contractor 5,061,277.35 15,845.76 10. Reduction Amt to Escrow -226,880.00 0.00 11. Payment to Escrow 226,880.00 12. Net Pymt. this Estimate 15,845.76