Dept. of Trans. PROGRESS Serial No. Contract No. 05-297-13-48 07-002594 PROGRESS PAYMENT VOUCHER %complete: %time: Location: PEP SAT 07-LA-101-13.2/14.9 Federal Project: ACNH-Q101(45) Progress payment No. 23 Payment period ending: 10-20-05 D W POWELL CONSTRUCTION INC P O BOX 1406 FONTANA CA 923341406 Escrow No. 02148 Total Estimate This Estimate 1. Contract Itms Without Mobil. 9,796,962.87 691,859.50 2.a. Extra Work 427,165.47 11,340.95 b. Adjustment Comp. 67,894.97 0.00 3. Materials on Hand 154,818.37 4,713.37 4. Earned Subject to Retention 10,446,841.68 707,913.82 5. Mobilization 950,000.00 0.00 6. Total Work Completed 11,242,023.31 7. Deductions -5,000.00 0.00 8. a.Contract Retentions -522,342.08 -33,245.30 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 10,869,499.60 674,668.52 10. Reduction Amt to Escrow 11. Payment to Escrow 522,340.00 12. Net Pymt. this Estimate 674,668.52