Dept. of Trans. PROGRESS Serial No. Contract No. 04-146-12-22 07-0239A4 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 21% 41% 07-LA-60-21.8/22.3 Federal Project: ACNH-P060(124) Progress payment No. 04 Payment period ending: 05-20-04 PETERSON CHASE GENERAL ENGINEERING CONSTRUCTION INC 1792 KAISER AVENUE IRVINE CA 926145706 Escrow No. 02159 Total Estimate This Estimate 1. Contract Itms Without Mobil. 234,150.80 117,750.80 2.a. Extra Work 2,010.18 2,010.18 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 236,160.98 119,760.98 5. Mobilization 90,000.00 30,000.00 6. Total Work Completed 326,160.98 7. Deductions 8. a.Contract Retentions -23,616.10 -11,976.10 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 302,544.88 137,784.88 10. Reduction Amt to Escrow 11. Payment to Escrow 23,610.00 12. Net Pymt. this Estimate 137,784.88