Dept. of Trans. PROGRESS Serial No. Contract No. 05-173-09-23 07-040104 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 17% 9% 07-LA-605-R14.6/R15.4 Federal Project: ACIM-605-2(720) Progress payment No. 06 Payment period ending: 06-20-05 PKB CONSTRUCTION INC P O BOX 661717 ARCADIA CA 91066 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 486,297.86 123,405.00 2.a. Extra Work 9,440.98 2,019.97 b. Adjustment Comp. 3. Materials on Hand 10,415.00 0.00 4. Earned Subject to Retention 506,153.84 125,424.97 5. Mobilization 346,323.75 115,441.25 6. Total Work Completed 842,062.59 7. Deductions -10,000.00 -10,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 842,477.59 230,866.22 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 230,866.22