Dept. of Trans. PROGRESS Serial No. Contract No. 06-360-07-59 07-040104 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 96% 89% 07-LA-605-R14.6/R15.4 Federal Project: ACIM-605-2(720) Progress payment No. 25 Payment period ending: 12-20-06 PKB CONSTRUCTION INC P O BOX 661717 ARCADIA CA 91066 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 4,268,898.99 193,833.80 2.a. Extra Work 201,551.37 15,518.65 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 4,470,450.36 209,352.45 5. Mobilization 461,765.00 0.00 6. Total Work Completed 4,932,215.36 7. Deductions 0.00 10,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 4,932,215.36 219,352.45 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 219,352.45