Dept. of Trans. PROGRESS Serial No. Contract No. 04-146-12-22 07-0510A4 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 16% 25% 07-LA-5-28.1/28.6 Federal Project: ACIM-005-3(45) Progress payment No. 03 Payment period ending: 05-20-04 O DONNELL CONSTRUCTION INC 559 W COVINA BLVD SAN DIMAS CA 917732911 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 427,177.00 179,595.00 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 427,177.00 179,595.00 5. Mobilization 285,000.00 95,000.00 6. Total Work Completed 712,177.00 7. Deductions -10,000.00 -10,000.00 8. a.Contract Retentions -42,717.70 -17,959.50 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 659,459.30 246,635.50 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 246,635.50