Dept. of Trans. PROGRESS Serial No. Contract No. 05-027-07-33 07-0510A4 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 50% 75% 07-LA-5-28.1/28.6 Federal Project: ACIM-005-3(45) Progress payment No. 11 Payment period ending: 01-20-05 O DONNELL CONSTRUCTION INC 559 W COVINA BLVD SAN DIMAS CA 917732911 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,782,461.80 74,070.00 2.a. Extra Work 116,132.82 39,942.03 b. Adjustment Comp. 3. Materials on Hand 17,389.89 17,389.89 4. Earned Subject to Retention 1,915,984.51 131,401.92 5. Mobilization 361,000.00 0.00 6. Total Work Completed 2,259,594.62 7. Deductions 8. a.Contract Retentions -95,799.23 -6,570.10 b. Unsatisfactory Prog. -34,478.73 -6,570.09 c. Reduction after 95% Comp. 9. Total pay to Contractor 2,146,706.55 118,261.73 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 118,261.73