Dept. of Trans. PROGRESS Serial No. Contract No. 03-358-11-07 07-053344 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 46% 90% 07-LA-101-15.4/15.9 Federal Project: ACNH-Q101(15) Progress payment No. 07 Payment period ending: 12-20-03 D W POWELL CONSTRUCTION INC P O BOX 1406 FONTANA CA 923341406 Escrow No. 02045 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,185,159.90 617,183.60 2.a. Extra Work 3,970.36 0.00 b. Adjustment Comp. -2,302.60 -5,042.60 3. Materials on Hand 14,681.00 -17,044.00 4. Earned Subject to Retention 1,201,508.66 595,097.00 5. Mobilization 285,000.00 60,000.00 6. Total Work Completed 1,471,827.66 7. Deductions 8. a.Contract Retentions -60,075.43 -1,750.36 b. Unsatisfactory Prog. -32,070.95 -29,754.85 c. Reduction after 95% Comp. 9. Total pay to Contractor 1,394,362.28 623,591.79 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 623,591.79