Dept. of Trans. PROGRESS Serial No. Contract No. 04-024-07-10 07-053344 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 53% 96% 07-LA-101-15.4/15.9 Federal Project: ACNH-Q101(15) Progress payment No. 08 Payment period ending: 01-20-04 D W POWELL CONSTRUCTION INC P O BOX 1406 FONTANA CA 923341406 Escrow No. 02045 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,422,407.90 237,248.00 2.a. Extra Work 6,966.92 2,996.56 b. Adjustment Comp. -2,302.60 0.00 3. Materials on Hand 38,476.62 23,795.62 4. Earned Subject to Retention 1,465,548.84 264,040.18 5. Mobilization 285,000.00 0.00 6. Total Work Completed 1,712,072.22 7. Deductions 8. a.Contract Retentions -73,277.44 -13,202.01 b. Unsatisfactory Prog. 0.00 32,070.95 c. Reduction after 95% Comp. 9. Total pay to Contractor 1,677,271.40 282,909.12 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 282,909.12