Dept. of Trans. PROGRESS Serial No. Contract No. 04-056-10-45 07-053344 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 53% 100% 07-LA-101-15.4/15.9 Federal Project: ACNH-Q101(15) Progress payment No. 09 Payment period ending: 02-20-04 D W POWELL CONSTRUCTION INC P O BOX 1406 FONTANA CA 923341406 Escrow No. 02045 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,431,387.90 8,980.00 2.a. Extra Work 6,966.92 0.00 b. Adjustment Comp. -2,302.60 0.00 3. Materials on Hand 49,122.52 10,645.90 4. Earned Subject to Retention 1,485,174.74 19,625.90 5. Mobilization 285,000.00 0.00 6. Total Work Completed 1,721,052.22 7. Deductions 8. a.Contract Retentions -74,258.74 -981.30 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 1,695,916.00 18,644.60 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 18,644.60