Dept. of Trans. PROGRESS Serial No. Contract No. 04-114-14-40 07-053344 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 66% 100% 07-LA-101-15.4/15.9 Federal Project: ACNH-Q101(15) Progress payment No. 11 Payment period ending: 04-20-04 D W POWELL CONSTRUCTION INC P O BOX 1406 FONTANA CA 923341406 Escrow No. 02045 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,824,677.50 378,063.60 2.a. Extra Work 20,030.14 508.87 b. Adjustment Comp. -2,302.60 0.00 3. Materials on Hand 17,079.84 -32,042.68 4. Earned Subject to Retention 1,859,484.88 346,529.79 5. Mobilization 300,000.00 15,000.00 6. Total Work Completed 2,142,405.04 7. Deductions -10,000.00 -8,477.40 8. a.Contract Retentions -92,974.24 -17,326.49 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 2,056,510.64 335,725.90 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 335,725.90