Dept. of Trans. PROGRESS Serial No. Contract No. 04-173-14-43 07-053344 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 74% 85% 07-LA-101-15.4/15.9 Federal Project: ACNH-Q101(15) Progress payment No. 13 Payment period ending: 06-20-04 D W POWELL CONSTRUCTION INC P O BOX 1406 FONTANA CA 923341406 Escrow No. 02045 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2,089,740.30 84,249.20 2.a. Extra Work 20,421.14 0.00 b. Adjustment Comp. -2,302.60 0.00 3. Materials on Hand 4. Earned Subject to Retention 2,107,858.84 84,249.20 5. Mobilization 300,000.00 0.00 6. Total Work Completed 2,407,858.84 7. Deductions 8. a.Contract Retentions -105,392.94 -4,212.46 b. Unsatisfactory Prog. -4,212.46 -4,212.46 c. Reduction after 95% Comp. 9. Total pay to Contractor 2,298,253.44 75,824.28 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 75,824.28