Dept. of Trans. PROGRESS Serial No. Contract No. 04-267-09-38 07-053344 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 97% 100% 07-LA-101-15.4/15.9 Federal Project: ACNH-Q101(15) Progress payment No. 16 Payment period ending: 09-20-04 D W POWELL CONSTRUCTION INC P O BOX 1406 FONTANA CA 923341406 Escrow No. 02045 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2,828,037.10 121,160.00 2.a. Extra Work 26,517.77 2,583.20 b. Adjustment Comp. 6,759.34 0.00 3. Materials on Hand 4. Earned Subject to Retention 2,861,314.21 123,743.20 5. Mobilization 300,000.00 0.00 6. Total Work Completed 3,161,314.21 7. Deductions -108,600.00 -93,600.00 8. a.Contract Retentions -143,065.71 -6,187.16 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 2,909,648.50 23,956.04 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 23,956.04