Dept. of Trans. PROGRESS Serial No. Contract No. 03-295-13-48 07-0607U4 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 29% 34% 07-VEN-101-22.0/R24.0 Federal Project: ACNH-Q101(5) Progress payment No. 20 Payment period ending: 10-20-03 M C M SECURITY PAVING J V P O BOX 620 NORTH HIGHLANDS CA 95660 Escrow No. 01923 Total Estimate This Estimate 1. Contract Itms Without Mobil. 15,302,523.35 1,509,240.41 2.a. Extra Work 193,897.63 0.00 b. Adjustment Comp. 3. Materials on Hand 2,809,350.02 -15,161.56 4. Earned Subject to Retention 18,305,771.00 1,494,078.85 5. Mobilization 6,269,053.80 0.00 6. Total Work Completed 21,765,474.78 7. Deductions 8. a.Contract Retentions -1,349,510.76 0.00 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 23,225,314.04 1,494,078.85 10. Reduction Amt to Escrow 11. Payment to Escrow 1,349,510.00 12. Net Pymt. this Estimate 1,494,078.85