Dept. of Trans. PROGRESS Serial No. Contract No. 06-081-12-40 07-0607U4 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 79% 77% 07-VEN-101-22.0/R24.0 Federal Project: ACNH-Q101(5) Progress payment No. 54 Payment period ending: 03-20-06 M C M SECURITY PAVING J V P O BOX 620 NORTH HIGHLANDS CA 95660 Escrow No. 01923 Total Estimate This Estimate 1. Contract Itms Without Mobil. 52,625,353.94 490,603.21 2.a. Extra Work 4,797,905.93 29,160.26 b. Adjustment Comp. 654,522.85 -64,411.50 3. Materials on Hand 1,326,940.00 -4,800.00 4. Earned Subject to Retention 59,404,722.72 450,551.97 5. Mobilization 6,599,004.00 0.00 6. Total Work Completed 64,676,786.72 7. Deductions -13,112.86 0.00 8. a.Contract Retentions -2,970,236.14 -22,527.60 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 63,020,377.72 428,024.37 10. Reduction Amt to Escrow 11. Payment to Escrow 2,970,230.00 12. Net Pymt. this Estimate 428,024.37