Dept. of Trans. PROGRESS Serial No. Contract No. 03-113-14-07 07-061744 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 14% 40% 07-LA-134-0.0/2.1 Federal Project: ACNH-X037(111) Progress payment No. 05 Payment period ending: 04-20-03 ORTIZ ENTERPRISES INCORPORATED 6 CUSHING SUITE 200 IRVINE CA 92618 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 543,435.79 112,252.79 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 543,435.79 112,252.79 5. Mobilization 301,485.00 0.00 6. Total Work Completed 844,920.79 7. Deductions -10,000.00 10,000.00 8. a.Contract Retentions -54,343.58 -11,225.28 b. Unsatisfactory Prog. -0.01 0.00 c. Reduction after 95% Comp. 9. Total pay to Contractor 780,577.20 111,027.51 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 111,027.51