Dept. of Trans. PROGRESS Serial No. Contract No. 04-238-11-56 07-066324 PROGRESS PAYMENT VOUCHER %complete: %time: Location: PEP SAT 07-LA-10-38.5/38.9 Federal Project: ACIM-010-1(770) Progress payment No. 13 Payment period ending: 08-20-04 D W POWELL CONSTRUCTION INC P O BOX 1406 FONTANA CA 923341406 Escrow No. 02116 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,390,604.10 2,048.00 2.a. Extra Work 45,539.68 0.00 b. Adjustment Comp. -3,027.50 0.00 3. Materials on Hand 4. Earned Subject to Retention 1,433,116.28 2,048.00 5. Mobilization 140,000.00 0.00 6. Total Work Completed 1,573,116.28 7. Deductions -2,492.70 -1,000.00 8. a.Contract Retentions -71,655.81 -102.40 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 1,498,967.77 945.60 10. Reduction Amt to Escrow 11. Payment to Escrow 71,550.00 12. Net Pymt. this Estimate 945.60