Dept. of Trans. PROGRESS Serial No. Contract No. 04-266-10-36 07-066324 PROGRESS PAYMENT VOUCHER %complete: %time: Location: PEP SAT 07-LA-10-38.5/38.9 Federal Project: ACIM-010-1(770) Progress payment No. 14 Payment period ending: 09-20-04 D W POWELL CONSTRUCTION INC P O BOX 1406 FONTANA CA 923341406 Escrow No. 02116 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,392,364.10 1,760.00 2.a. Extra Work 46,933.80 1,394.12 b. Adjustment Comp. -3,027.50 0.00 3. Materials on Hand 4. Earned Subject to Retention 1,436,270.40 3,154.12 5. Mobilization 140,000.00 0.00 6. Total Work Completed 1,576,270.40 7. Deductions -2,492.70 0.00 8. a.Contract Retentions -71,813.52 -157.71 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 1,501,964.18 2,996.41 10. Reduction Amt to Escrow 11. Payment to Escrow 71,550.00 12. Net Pymt. this Estimate 2,996.41