Dept. of Trans. FINAL Serial No. Contract No. 05-230-13-05 07-066324 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 07-LA-10-38.5/38.9 Federal Project: ACIM-010-1(770) Progress payment No. 18 Payment period ending: 11-04-04 D W POWELL CONSTRUCTION INC P O BOX 1406 FONTANA CA 923341406 Escrow No. 02116 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,402,490.70 0.00 2.a. Extra Work 49,928.74 0.00 b. Adjustment Comp. 9,814.88 0.00 3. Materials on Hand 4. Earned Subject to Retention 1,462,234.32 0.00 5. Mobilization 140,000.00 0.00 6. Total Work Completed 1,602,234.32 7. Deductions 8. a.Contract Retentions -72,122.07 0.00 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 72,122.07 0.00 9. Total pay to Contractor 1,602,234.32 0.00 10. Reduction Amt to Escrow -72,120.00 0.00 11. Payment to Escrow 72,120.00 12. Net Pymt. this Estimate 0.00