Dept. of Trans. PROGRESS Serial No. Contract No. 11-294-17-23 07-0AA074 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 98% 100% 07-LA-5719 Federal Project: NONE Progress payment No. 02 Payment period ending: 10-18-11 METROCELL CONSTRUCTION INC 8104 FREESTONE AVENUE SANTA FE SPRINGS CA 90670 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 232,927.50 53,752.50 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 232,927.50 53,752.50 5. Mobilization 6. Total Work Completed 232,927.50 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. 0.00 17,917.50 c. Reduction after 95% Comp. 9. Total pay to Contractor 232,927.50 71,670.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 71,670.00