Dept. of Trans. PROGRESS Serial No. Contract No. 23-204-15-14 07-0W1204 PROGRESS PAYMENT VOUCHER %complete: %time: 91% 70% Location: Federal Project: 07-LA-2-24.4/46.0 NONE Progress payment No. 004 Payment period ending: 07-20-23 INTERMOUNTAIN SLURRY SEAL INC PO BOX 742298 LOS ANGELES CA 90074 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2,796,863.04 563,938.00 2. a. Extra Work 46,946.99 46,946.99 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 2,843,810.03 610,884.99 5. Mobilization 350,000.00 0.00 6. Total Work Completed 3,193,810.03 7. Deductions -6,193.00 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 3,187,617.03 610,884.99 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 610,884.99