Dept. of Trans. PROGRESS Serial No. Contract No. 24-023-08-15 07-0W2004 PROGRESS PAYMENT VOUCHER %complete: %time: 54% 60% Location: Federal Project: 07-LA-105-R0.1/R17.3 NONE Progress payment No. 005 Payment period ending: 01-20-24 PETERSON-CHASE GEN ENGINEERING CONSTRUCTION INC 16351 CONSTRUCTION CIR WEST IRVINE CA 92606-4414 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 421,459.00 290,548.00 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 118,212.46 -151,603.40 4. Earned Subject to Retention 539,671.46 138,944.60 5. Mobilization 67,000.00 0.00 6. Total Work Completed 488,459.00 7. Deductions -63,650.00 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 543,021.46 138,944.60 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 138,944.60