Dept. of Trans. PROGRESS Serial No. Contract No. 24-059-15-18 07-0W2004 PROGRESS PAYMENT VOUCHER %complete: %time: 81% 79% Location: Federal Project: 07-LA-105-R0.1/R17.3 NONE Progress payment No. 006 Payment period ending: 02-20-24 PETERSON-CHASE GEN ENGINEERING CONSTRUCTION INC 16351 CONSTRUCTION CIR WEST IRVINE CA 92606-4414 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 516,787.40 95,328.40 2. a. Extra Work b. Adustment Comp. 148,713.47 148,713.47 3. Materials on Hand 0.00 -118,212.46 4. Earned Subject to Retention 665,500.87 125,829.41 5. Mobilization 67,000.00 0.00 6. Total Work Completed 732,500.87 7. Deductions -63,650.00 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 668,850.87 125,829.41 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 125,829.41