Dept. of Trans. AFTER ACCEPTANCE Serial No. Contract No. 24-351-11-04 07-0W2704 PROGRESS PAYMENT VOUCHER %complete: %time: 100% 100% Location: Federal Project: 07-LA-710-10.5/R32.5 NONE Progress payment No. 012 Payment period ending: 09-26-24 PETERSON-CHASE GEN ENGINEERING CONSTRUCTION INC 16351 CONSTRUCTION CIR WEST IRVINE CA 92606-4414 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 3,357,354.04 -27,000.32 2. a. Extra Work 199,136.97 0.00 b. Adustment Comp. 951.64 0.00 3. Materials on Hand 4. Earned Subject to Retention 3,557,442.65 -27,000.32 5. Mobilization 197,000.00 0.00 6. Total Work Completed 3,754,442.65 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 3,754,442.65 -27,000.32 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate -27,000.32