Dept. of Trans. PROGRESS Serial No. Contract No. 25-233-07-46 07-0W2904 PROGRESS PAYMENT VOUCHER %complete: %time: 95% 95% Location: Federal Project: 07-LA-101-1.5/10.9 NONE Progress payment No. 022 Payment period ending: 08-20-25 PETERSON-CHASE GEN ENGINEERING CONSTRUCTION INC 16351 CONSTRUCTION CIR WEST IRVINE CA 92606-4414 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 5,351,556.85 15,175.00 2. a. Extra Work 494,506.31 155,535.65 b. Adustment Comp. 3. Materials on Hand 0.00 -60,624.26 4. Earned Subject to Retention 5,846,063.16 110,086.39 5. Mobilization 550,000.00 0.00 6. Total Work Completed 6,396,063.16 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 6,396,063.16 110,086.39 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 110,086.39