Dept. of Trans. PROGRESS Serial No. Contract No. 24-054-15-56 07-0W3004 PROGRESS PAYMENT VOUCHER %complete: %time: 44% 47% Location: Federal Project: 07-VAR-101-12.3/37.6 NONE Progress payment No. 004 Payment period ending: 02-20-24 VELARDE CONCRETE CONSTRUCTION INC 523 S. BRAND BLVD, #201 SAN FERNANDO CA 91340 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 485,420.17 77,700.73 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 287,895.78 -15,289.86 4. Earned Subject to Retention 773,315.95 62,410.87 5. Mobilization 164,246.85 8,212.34 6. Total Work Completed 649,667.02 7. Deductions -28,852.70 -942.64 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 908,710.10 69,680.57 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 69,680.57