Dept. of Trans. PROGRESS Serial No. Contract No. 24-081-09-30 07-0W3004 PROGRESS PAYMENT VOUCHER %complete: %time: 56% 59% Location: Federal Project: 07-VAR-101-12.3/37.6 NONE Progress payment No. 005 Payment period ending: 03-20-24 VELARDE CONCRETE CONSTRUCTION INC 523 S. BRAND BLVD, #201 SAN FERNANDO CA 91340 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 658,787.91 173,367.74 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 249,007.46 -38,888.32 4. Earned Subject to Retention 907,795.37 134,479.42 5. Mobilization 164,246.85 0.00 6. Total Work Completed 823,034.76 7. Deductions -28,852.70 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 1,043,189.52 134,479.42 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 134,479.42