Dept. of Trans. PROGRESS Serial No. Contract No. 24-022-15-14 07-0W3304 PROGRESS PAYMENT VOUCHER %complete: %time: 70% 54% Location: Federal Project: 07-LA-10-19.5/29.5 NONE Progress payment No. 007 Payment period ending: 01-20-24 GRIFFITH COMPANY 3050 E BIRCH ST BREA CA 92821 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 5,979,423.74 150,420.00 2. a. Extra Work 6,118.12 0.00 b. Adustment Comp. -5,000.00 0.00 3. Materials on Hand 4. Earned Subject to Retention 5,980,541.86 150,420.00 5. Mobilization 783,000.00 0.00 6. Total Work Completed 6,763,541.86 7. Deductions -58,000.00 -58,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 6,705,541.86 92,420.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 92,420.00