Dept. of Trans. PROGRESS Serial No. Contract No. 24-145-13-05 07-0W4704 PROGRESS PAYMENT VOUCHER %complete: %time: 48% 100% Location: Federal Project: 07-VAR-101-0.0/30.0 NONE Progress payment No. 009 Payment period ending: 05-20-24 GBA ENGINEERING 18543 YORBA LINDA BLVD - 394 YORBA LINDA CA 92886 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 607,265.00 35,997.00 2. a. Extra Work 1,200.00 0.00 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 608,465.00 35,997.00 5. Mobilization 30,000.00 0.00 6. Total Work Completed 638,465.00 7. Deductions -23,000.00 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 615,465.00 35,997.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 35,997.00