Dept. of Trans. PROGRESS Serial No. Contract No. 24-082-12-41 07-0W4804 PROGRESS PAYMENT VOUCHER %complete: %time: 85% 93% Location: Federal Project: 07-VAR-118-2.6/11.9 NONE Progress payment No. 003 Payment period ending: 03-20-24 JABRE CONTRACTING INC 1813 MANZANITA LN MANHATTAN BEACH CA 90266 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 376,172.00 331,452.00 2. a. Extra Work 22,776.41 0.00 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 398,948.41 331,452.00 5. Mobilization 40,000.00 10,000.00 6. Total Work Completed 438,948.41 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 438,948.41 341,452.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 341,452.00