Dept. of Trans. PROGRESS Serial No. Contract No. 25-167-08-23 07-0W6504 PROGRESS PAYMENT VOUCHER %complete: %time: 30% 54% Location: Federal Project: 07-VAR NONE Progress payment No. 008 Payment period ending: 06-20-25 PETERSON-CHASE GEN ENGINEERING CONSTRUCTION INC 16351 CONSTRUCTION CIR WEST IRVINE CA 92606-4414 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 828,505.26 0.00 2. a. Extra Work 39,615.72 23,788.35 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 868,120.98 23,788.35 5. Mobilization 230,850.00 0.00 6. Total Work Completed 1,098,970.98 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 1,098,970.98 23,788.35 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 23,788.35