Dept. of Trans. PROGRESS Serial No. Contract No. 25-260-17-45 07-0Y1804 PROGRESS PAYMENT VOUCHER %complete: %time: 47% 46% Location: Federal Project: 07-LA-60-0.0/R3.3 NONE Progress payment No. 002 Payment period ending: 09-20-25 PAVEMENT COATINGS CO. PO BOX 849485 LOS ANGELES CA 90084-9485 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 664,662.57 641,412.57 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 664,662.57 641,412.57 5. Mobilization 47,500.00 47,500.00 6. Total Work Completed 712,162.57 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 712,162.57 688,912.57 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 688,912.57