Dept. of Trans. AFTER ACCEPTANCE Serial No. Contract No. 05-125-07-22 07-101964 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 07-LA-101-11.5/12.0 Federal Project: ACNH-Q101(42) Progress payment No. 20 Payment period ending: 03-02-05 BRUTOCO ENGINEERING AND CONSTRUCTION INC P O BOX 429 FONTANA CA 92334 Escrow No. 02141 Total Estimate This Estimate 1. Contract Itms Without Mobil. 4,176,066.65 0.00 2.a. Extra Work 146,567.64 5,188.16 b. Adjustment Comp. 19,638.96 -4,325.38 3. Materials on Hand 4. Earned Subject to Retention 4,342,273.25 862.78 5. Mobilization 430,000.00 0.00 6. Total Work Completed 4,772,273.25 7. Deductions -2,000.00 2,325.38 8. a.Contract Retentions -216,377.86 0.00 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 216,377.86 0.00 9. Total pay to Contractor 4,770,273.25 3,188.16 10. Reduction Amt to Escrow -216,370.00 0.00 11. Payment to Escrow 216,370.00 12. Net Pymt. this Estimate 3,188.16