Dept. of Trans. PROGRESS Serial No. Contract No. 02-268-14-37 07-104954 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 1% 7% 07-VEN-101-12.8/14.2 Federal Project: ACNH-P101(996) Progress payment No. 02 Payment period ending: 09-20-02 SECURITY PAVING COMPANY INC P O BOX 1489 SUN VALLEY CA 913531489 Escrow No. 01969 Total Estimate This Estimate 1. Contract Itms Without Mobil. 204,314.53 175,914.53 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 204,314.53 175,914.53 5. Mobilization 6. Total Work Completed 204,314.53 7. Deductions -17,000.00 -17,000.00 8. a.Contract Retentions -20,431.45 -17,591.45 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 166,883.08 141,323.08 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 141,323.08