Dept. of Trans. PROGRESS Serial No. Contract No. 03-203-13-11 07-104954 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 32% 42% 07-VEN-101-12.8/14.2 Federal Project: ACNH-P101(996) Progress payment No. 12 Payment period ending: 07-20-03 SECURITY PAVING COMPANY INC P O BOX 1489 SUN VALLEY CA 913531489 Escrow No. 01969 Total Estimate This Estimate 1. Contract Itms Without Mobil. 4,592,171.24 457,553.25 2.a. Extra Work 429,428.24 82,490.25 b. Adjustment Comp. -16,744.02 -56,797.88 3. Materials on Hand 142,301.82 0.00 4. Earned Subject to Retention 5,147,157.28 483,245.62 5. Mobilization 636,500.00 0.00 6. Total Work Completed 5,641,355.46 7. Deductions -63,300.00 -15,000.00 8. a.Contract Retentions -305,789.98 0.00 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 5,414,567.30 468,245.62 10. Reduction Amt to Escrow 11. Payment to Escrow 305,780.00 12. Net Pymt. this Estimate 468,245.62