Dept. of Trans. PROGRESS Serial No. Contract No. 03-237-12-52 07-104954 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 34% 46% 07-VEN-101-12.8/14.2 Federal Project: ACNH-P101(996) Progress payment No. 13 Payment period ending: 08-20-03 SECURITY PAVING COMPANY INC P O BOX 1489 SUN VALLEY CA 913531489 Escrow No. 01969 Total Estimate This Estimate 1. Contract Itms Without Mobil. 4,994,281.99 402,110.75 2.a. Extra Work 465,424.02 35,995.78 b. Adjustment Comp. -16,744.02 0.00 3. Materials on Hand 126,782.61 -15,519.21 4. Earned Subject to Retention 5,569,744.60 422,587.32 5. Mobilization 636,500.00 0.00 6. Total Work Completed 6,079,461.99 7. Deductions -44,550.00 18,750.00 8. a.Contract Retentions -305,789.98 0.00 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 5,855,904.62 441,337.32 10. Reduction Amt to Escrow 11. Payment to Escrow 305,780.00 12. Net Pymt. this Estimate 441,337.32