Dept. of Trans. PROGRESS Serial No. Contract No. 03-267-14-20 07-104954 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 38% 50% 07-VEN-101-12.8/14.2 Federal Project: ACNH-P101(996) Progress payment No. 14 Payment period ending: 09-20-03 SECURITY PAVING COMPANY INC P O BOX 1489 SUN VALLEY CA 913531489 Escrow No. 01969 Total Estimate This Estimate 1. Contract Itms Without Mobil. 5,670,623.61 676,341.62 2.a. Extra Work 465,424.02 0.00 b. Adjustment Comp. -16,744.02 0.00 3. Materials on Hand 87,861.78 -38,920.83 4. Earned Subject to Retention 6,207,165.39 637,420.79 5. Mobilization 636,500.00 0.00 6. Total Work Completed 6,755,803.61 7. Deductions -55,800.00 -11,250.00 8. a.Contract Retentions -310,358.27 -4,568.29 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 6,477,507.12 621,602.50 10. Reduction Amt to Escrow 11. Payment to Escrow 310,350.00 12. Net Pymt. this Estimate 621,602.50