Dept. of Trans. PROGRESS Serial No. Contract No. 04-084-08-41 07-104954 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 61% 64% 07-VEN-101-12.8/14.2 Federal Project: ACNH-P101(996) Progress payment No. 20 Payment period ending: 03-20-04 SECURITY PAVING COMPANY INC P O BOX 1489 SUN VALLEY CA 913531489 Escrow No. 01969 Total Estimate This Estimate 1. Contract Itms Without Mobil. 9,023,494.75 676,388.16 2.a. Extra Work 1,572,352.27 405,610.81 b. Adjustment Comp. -57,347.17 0.00 3. Materials on Hand 77,161.00 0.00 4. Earned Subject to Retention 10,615,660.85 1,081,998.97 5. Mobilization 670,000.00 0.00 6. Total Work Completed 11,208,499.85 7. Deductions -62,050.00 -10,000.00 8. a.Contract Retentions -530,783.04 -54,099.95 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 10,692,827.81 1,017,899.02 10. Reduction Amt to Escrow 11. Payment to Escrow 530,780.00 12. Net Pymt. this Estimate 1,017,899.02