Dept. of Trans. PROGRESS Serial No. Contract No. 04-173-14-43 07-104954 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 72% 75% 07-VEN-101-12.8/14.2 Federal Project: ACNH-P101(996) Progress payment No. 23 Payment period ending: 06-20-04 SECURITY PAVING COMPANY INC P O BOX 1489 SUN VALLEY CA 913531489 Escrow No. 01969 Total Estimate This Estimate 1. Contract Itms Without Mobil. 11,165,840.98 928,694.47 2.a. Extra Work 1,659,136.11 10,560.45 b. Adjustment Comp. -43,664.94 0.00 3. Materials on Hand 77,161.00 0.00 4. Earned Subject to Retention 12,858,473.15 939,254.92 5. Mobilization 670,000.00 0.00 6. Total Work Completed 13,451,312.15 7. Deductions -67,050.00 0.00 8. a.Contract Retentions -642,923.66 -46,962.75 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 12,818,499.49 892,292.17 10. Reduction Amt to Escrow 11. Payment to Escrow 642,920.00 12. Net Pymt. this Estimate 892,292.17