Dept. of Trans. AFTER ACCEPTANCE Serial No. Contract No. 06-194-14-05 07-104954 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 07-VEN-101-12.8/14.2 Federal Project: ACNH-P101(996) Progress payment No. 49 Payment period ending: 06-26-06 SECURITY PAVING COMPANY INC P O BOX 1489 SUN VALLEY CA 913531489 Escrow No. 01969 Total Estimate This Estimate 1. Contract Itms Without Mobil. 15,910,228.08 -465.17 2.a. Extra Work 3,402,078.95 187,035.29 b. Adjustment Comp. 88,466.90 -31,080.38 3. Materials on Hand 4. Earned Subject to Retention 19,400,773.93 155,489.74 5. Mobilization 670,000.00 0.00 6. Total Work Completed 20,070,773.93 7. Deductions -43,988.00 15,750.00 8. a.Contract Retentions -962,264.21 0.00 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 962,264.21 962,264.21 9. Total pay to Contractor 20,026,785.93 1,133,503.95 10. Reduction Amt to Escrow -962,260.00 -962,260.00 11. Payment to Escrow 962,260.00 12. Net Pymt. this Estimate 171,243.95