Dept. of Trans. PROGRESS Serial No. Contract No. 05-055-07-25 07-105484 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 99% 68% 07-VEN-150-15.0/23.9 Federal Project: ACST-P150(18) Progress payment No. 10 Payment period ending: 02-20-05 FNF CONSTRUCTION INC P O BOX 5005 TEMPE AZ 85280 Escrow No. 01980 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2,199,952.10 7,500.00 2.a. Extra Work 287,032.65 0.00 b. Adjustment Comp. 9,316.74 0.00 3. Materials on Hand 4. Earned Subject to Retention 2,496,301.49 7,500.00 5. Mobilization 235,000.00 0.00 6. Total Work Completed 2,731,301.49 7. Deductions 8. a.Contract Retentions -124,815.07 -375.00 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 2,606,486.42 7,125.00 10. Reduction Amt to Escrow 11. Payment to Escrow 124,810.00 12. Net Pymt. this Estimate 7,125.00