Dept. of Trans. SUPPLEMENTAL Serial No. Contract No. 02-252-13-53 07-1069U4 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 26% 19% 07-LA-10-28.0/31.2 Federal Project: ACNH-010-1(762) I-010-1(762) Progress payment No. 10 Payment period ending: 08-20-02 E L YEAGER CONSTRUCTION COMPANY INC P O BOX 87 RIVERSIDE CA 925020087 Escrow No. 01885 Total Estimate This Estimate 1. Contract Itms Without Mobil. 7,829,388.67 219,220.30 2.a. Extra Work 106,301.58 -2,016.69 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 7,935,690.25 217,203.61 5. Mobilization 2,784,000.00 0.00 6. Total Work Completed 10,719,690.25 7. Deductions 8. a.Contract Retentions -763,382.50 0.00 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 9,956,307.75 217,203.61 10. Reduction Amt to Escrow 11. Payment to Escrow 600,000.00 12. Net Pymt. this Estimate 217,203.61