Dept. of Trans. PROGRESS Serial No. Contract No. 02-327-07-27 07-1069U4 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 37% 28% 07-LA-10-28.0/31.2 Federal Project: ACNH-010-1(762) I-010-1(762) Progress payment No. 13 Payment period ending: 11-20-02 E L YEAGER CONSTRUCTION COMPANY INC P O BOX 87 RIVERSIDE CA 925020087 Escrow No. 01885 Total Estimate This Estimate 1. Contract Itms Without Mobil. 11,677,426.11 1,181,980.06 2.a. Extra Work 266,471.99 35,692.92 b. Adjustment Comp. 1,760.15 0.00 3. Materials on Hand 35,081.77 35,081.77 4. Earned Subject to Retention 11,980,740.02 1,252,754.75 5. Mobilization 3,526,400.00 0.00 6. Total Work Completed 15,472,058.25 7. Deductions 0.00 10,000.00 8. a.Contract Retentions -763,382.50 0.00 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 14,743,757.52 1,262,754.75 10. Reduction Amt to Escrow 11. Payment to Escrow 600,000.00 12. Net Pymt. this Estimate 1,262,754.75