Dept. of Trans. PROGRESS Serial No. Contract No. 03-171-12-14 07-1069U4 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 57% 47% 07-LA-10-28.0/31.2 Federal Project: ACNH-010-1(762) I-010-1(762) Progress payment No. 22 Payment period ending: 06-20-03 E L YEAGER CONSTRUCTION COMPANY INC P O BOX 87 RIVERSIDE CA 925020087 Escrow No. 01885 Total Estimate This Estimate 1. Contract Itms Without Mobil. 19,930,390.21 1,713,566.22 2.a. Extra Work 533,580.58 20,765.90 b. Adjustment Comp. -8,106.18 1,212.31 3. Materials on Hand 411,831.58 0.00 4. Earned Subject to Retention 20,867,696.19 1,735,544.43 5. Mobilization 3,712,000.00 185,600.00 6. Total Work Completed 24,167,864.61 7. Deductions -46,240.00 -10,000.00 8. a.Contract Retentions -1,043,384.81 -86,777.22 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 23,490,071.38 1,824,367.21 10. Reduction Amt to Escrow 11. Payment to Escrow 1,000,000.00 12. Net Pymt. this Estimate 1,824,367.21