Dept. of Trans. PROGRESS Serial No. Contract No. 03-237-11-52 07-1069U4 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 62% 53% 07-LA-10-28.0/31.2 Federal Project: ACNH-010-1(762) I-010-1(762) Progress payment No. 24 Payment period ending: 08-20-03 E L YEAGER CONSTRUCTION COMPANY INC P O BOX 87 RIVERSIDE CA 925020087 Escrow No. 01885 Total Estimate This Estimate 1. Contract Itms Without Mobil. 22,131,147.79 1,357,299.23 2.a. Extra Work 578,552.37 13,704.12 b. Adjustment Comp. 4,817.35 12,923.53 3. Materials on Hand 342,940.00 -68,891.58 4. Earned Subject to Retention 23,057,457.51 1,315,035.30 5. Mobilization 3,712,000.00 0.00 6. Total Work Completed 26,426,517.51 7. Deductions -46,240.00 0.00 8. a.Contract Retentions -1,152,872.88 -65,751.77 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 25,570,344.63 1,249,283.53 10. Reduction Amt to Escrow 11. Payment to Escrow 1,000,000.00 12. Net Pymt. this Estimate 1,249,283.53