Dept. of Trans. PROGRESS Serial No. Contract No. 05-360-14-25 07-1069U4 PROGRESS PAYMENT VOUCHER %complete: %time: Location: PEP SAT 07-LA-10-28.0/31.2 Federal Project: ACNH-010-1(762) I-010-1(762) Progress payment No. 52 Payment period ending: 12-20-05 E L YEAGER CONSTRUCTION COMPANY INC 1995 AGUA MANSA RD RIVERSIDE CA 925092405 Escrow No. 01885 Total Estimate This Estimate 1. Contract Itms Without Mobil. 38,317,872.36 6,640.00 2.a. Extra Work 2,314,737.19 10,187.80 b. Adjustment Comp. 635,735.42 0.00 3. Materials on Hand 4. Earned Subject to Retention 41,268,344.97 16,827.80 5. Mobilization 3,712,000.00 0.00 6. Total Work Completed 44,980,344.97 7. Deductions -12,456.47 0.00 8. a.Contract Retentions -2,063,417.25 -841.39 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 42,904,471.25 15,986.41 10. Reduction Amt to Escrow 11. Payment to Escrow 2,000,000.00 12. Net Pymt. this Estimate 15,986.41