Dept. of Trans. PROGRESS Serial No. Contract No. 02-171-07-04 07-1150U4 PROGRESS PAYMENT VOUCHER %complete: %time: Location: PEP SAT 07-LA-138-43.4/51.9 Federal Project: ACNH-P138(26) Progress payment No. 15 Payment period ending: 06-20-02 GRANITE CONSTRUCTION COMPANY P O BOX 50085 WATSONVILLE CA 950775085 Escrow No. 01635 Total Estimate This Estimate 1. Contract Itms Without Mobil. 6,455,027.98 61,950.00 2.a. Extra Work 393,674.75 57,258.10 b. Adjustment Comp. 10,070.44 -21,014.28 3. Materials on Hand 0.00 -58,327.40 4. Earned Subject to Retention 6,858,773.17 39,866.42 5. Mobilization 702,886.00 0.00 6. Total Work Completed 7,561,659.17 7. Deductions -10,000.00 0.00 8. a.Contract Retentions -342,938.66 -1,993.32 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 7,208,720.51 37,873.10 10. Reduction Amt to Escrow 11. Payment to Escrow 342,930.00 12. Net Pymt. this Estimate 37,873.10